|

|
|
7 March 2008
Basement walls have been back-filled and compressed ready for shuttering
for the ground floor slab. The ground floor slab will cover the basement
area plus the ground shown levelled in the photo. The internal shuttering
for the basement walls has also been removed.
|
|
|

|
|
7 March 2008
Same day as above, photo taken from the edge of the ground slab area.
The in-fill was rock hard core which was then compressed / rollered.
|
|
|

|
|
10 March 2008
Constructing the shuttering for the
ground floor slab
|
|
|

|
|
13 March 2008
Progress on the shuttering for the
ground floor slab.
The boards over the basement are held up by scaffolding and concrete will
be poured onto the boards
|
|
|

|
|
22 March 2008
Starting on the steel reinforcing work
|
|
|

|
|
23 March 2008
Inspection by two "experts"
|
|
|

|
|
30 March 2008
Iron work finished.
Ready for pouring concrete to make
the ground floor slab.
|
|
|

|
|
30 March 2008
Showing steel reinforcing detail
|
|
|

|
|
30 March 2008
Showing waste pipes within the base
Picture below shows room layouts
|
|
|

|
|
|

|
|
1 April 2008
Concrete poured for the ground floor slab on 30th March.
|
|
|

|
|
1 April 2008
Another view
|
|
|

|
|
1 April 2008
Stairs down to the basement from
the Kitchen.
|
|
|

|
|
1 April 2008
Stairs up from the basement.
|
|
|

|
|
1 April 2008
Part of the basement showing ceiling
(lounge floor) supports.
|
|
|

|
|
11 April 2008
Ironwork completed for the pillars.
Shuttering will now be constructed round the ironwork and then concrete
poured in.
Should be completed next week.
|
|
|

|
|
11 April 2008
Showing ironwork detail.
|
|
|

|
|
20 April 2008
Finishing off the shuttering for the pillars.
Update: Concrete was poured for the pillars
on 21 April.
|
|
|

|
|
25 April 2008
Shuttering removed. It is now Easter in Cyprus. Work will not resume
untill around 5 May.
|
|
|

|
|
25 April 2008
View of basement space from veranda.
In this space is the 'self contained' studio and the utility room. Mostly
out of site to the left is the storage / workshop space.
|
|
|

|
|
25 April 2008
View from inside the basement studio looking towards the studio veranda.
|
|
|

|
|
25 April 2008
Beyond the pillar is workshop / storage space with access from the veranda
and from inside.
|
|
|
|
|
Next Page May - Jun 08 |
|
|
|
|
|
|
 |
 |
 |
 |
 |