Custom Build Bungalow at Arodes

 

Click for Paphos, Cyprus Forecast

Click here for Jan 12 - to date    The Latest

Click here for Sep 11 - Dec 11    

Click here for Sep 10 - Aug 11    

Click here for Dec 09 - Jul 10

Click here for Aug - Nov 09

Click here for May - Jul 09

Click here for Feb - Mar 09

Click here for Dec - Jan 09

Click here for Oct - Nov 08

Click here for Jul - Sep 08

Click here for May - Jun 08

Click here for Mar - Apr 08

Click here for Jan - Feb 08

This page = Nov - Dec 07

Click Here for Sep - Oct 07 

Click here for Oct 06 - Aug 07   The Start

Click here for Plan View

 

 

 

 

 

2 November 2007

The steel work has been formed for the reinforcing of the base.
You can see the main drainage from the basement services laid within the base.

This is now ready for the concrete which will be poured within the next few days.

 

 

 

 

 
 

 

 

2 November 2007

Close up of the steel reinforcement.

 

 

 

 

 

 
 

 

 

2 November 2007

Another close-up showing a waste pipe within the steel work.

The concrete of this base will be half a metre (20 inches) thick.

 

 

 

 
 

 

 

5 November 2007

Concrete crane/pump in position with first concrete lorry ready to pour concrete into the basement floor slab.

 

 

 

 

 

 
 

 

 

5 November 2007

3 man operation. 1 directing the pouring, 1 controlling the crane/pump, and 1 dispensing the concrete into the crane/pump from the concrete lorry.

The bloke looking on thinks he's the foreman but they don't seem to take any notice of him.

I have this operation captured on video and will put a short sequence on the website as soon as able

 

 

 
 

 

 

5 November 2007

After 1 lorry load.

Click HERE for short video

 

 

 

 

 
 

 

 

5 November 2007

After 3 loads.

It took 5 and 1 quarter loads to complete.

 

 

 

 

 

 
 

 

 

12 November 2007

Base drying out

 

 

 

 

 

 

 
 

 

 

22 November 2007

Installing the shuttering for the pillars and basement walls. When the outside shuttering is complete, the steelwork will be extended and then shuttering installed on the inside. Concrete will then be poured between the shuttering.

 

 

 

 

 
 

 

 

22 November 2007

Another angle.

It's a clear day, you can see the sea in the distance

 

 

 

 

 

 
 

 

 

24 November 2007

Steel work for the walls and pillars extended.

 

 

 

 

 

 
 

 

 

30 November 2007

The inside shuttering for the walls is nearly complete

 

 

 

 

 

 
 

 

 

30 November 2007

 

 

 

 

 

 

 
 

 

 

30 November 2007

The concrete is scheduled to arrive next Monday 3rd December. This will be poured between the shuttering on all 4 walls plus the pillars.

 

 

 

 

 
 

 

 

8 December 2007

Oh dear! It hasn't stopped raining since the day the concrete was due. Has also caused some of the shuttering supports to collapse.

 

 

 

 

 

 
 
  Next Page   Jan - Feb 08