Custom Build Bungalow at Arodes

 

Click for Paphos, Cyprus Forecast

Click here for Jan 12 - to date    The Latest

Click here for Sep 11 - Dec 11    

Click here for Sep 10 - Aug 11   

Click here for Dec 09 - Jul 10

Click here for Aug - Nov 09

Click here for May - Jul 09

Click here for Feb - Mar 09

Click here for Dec - Jan 09

This page = Oct - Nov 08  

Click here for Jul - Sep 08

Click here for May - Jun 08

Click here for Mar - Apr 08

Click here for Jan - Feb 08

Click here for Nov - Dec 07

Click Here for Sep - Oct 07 

Click here for Oct 06 - Aug 07   The Start

Click here for Plan View

 

 

 

 

 

10 October 2008

Finishing coats of rendering on outside.

 

 

 

 

 
 

 

 

10 October 2008

More shuttering at end of veranda for retaining wall for the veranda base.

 

 

 

 

 

 
 

 

 

10 October 2008

Main fuse panel in lobby.

 

 

 

 

 

 
 

 

 

10 October 2008

All services now in. Electrical wiring completed and water pipes tested.

Next is the laying of approx 6" of foam concrete over the whole floor area.

 

 

 

 
 

 

 

17 October 2008

All floors covered with foam concrete.

 

 

 

 

 

 
 

 

 

Some of the plaques being inset into
the walls of the bungalow

 

 

 

 

 

 

 
 

 

 

24 October 2008

First coats of plaster completed in all rooms. This picture taken in the lounge.
The plastering should be finished in 1 week and then tiling will start on the floors. Tiles for all rooms have been chosen and ordered along with windows, and granite work tops for the kitchen.

 

 

 

 

 
 

 

 

24 October 2008

Preparing for verandas at the rear. The one outside the lounge is covered, with steps down to the other. Further steps lead down to the swimming pool where you can see the break in the retaining wall. The veranda floors should be laid in the next week and then the swimming pool will be excavated.

 

 

 

 
 

 

 

31 October 2008

Marble window sills fitted.

 

 

 

 

 
 

 

 

2 November 2008

Groundworks at the front.
Drives and levels in front of house.

 

 

 

 

 
 

 

 

2 November 2008

Plastering and first coat of paint finished in nearly all the rooms on the ground floor.

 

 

 

 

 
 

 

 

5 November 2008

Shuttering for main veranda at rear.

 

 

 

 

 
 

 

 

5 November 2008

Excavation for the swimming pool. The swimming pool is not built using shuttering, it is constructed using pre-built metal frames.

 

 

 

 

 
 

 

 

5 November 2008

The arrow points to the main sewerage pipe from the house. The cutting edge sceptic tank will be built here. We are also hoping to install a system that re-cycles 100% of grey water that can be used for cleaning cars, topping up the pool and irrigating the garden. This is expected to be compulsory in Cyprus within a couple of years and sounds a very good idea to us.

 

 

 
 

 

 

8 November 2008

The lounge from the kitchen.

The plastering is finished internally and we are now waiting for the tiler to start tiling all the floors.

 

 

 

 

 
 

 

 

8 November 2008

Drive in and out. Stamped concrete will be used in front of the house.

 

 

 

 

 
 

 

 

8 November 2008

Steel reinforcing completed for the verandas.

 

 

 

 

 
 

 

 

8 November 2008

Smaller veranda at the rear outside the office and bedroom.

 

 

 

 

 

 
 

 

 

14 November 2008

Veranda concreted and shuttering done for the columns which will support the roof of the covered veranda.

 

 

 

 

 
 

 

 

14 November 2008

Tiling laid in bedrooms, office and passage.

 

 

 

 

 

 

 
 

 

 

14 November 2008

Tiling laid in Master Bedroom.

 

 

 

 

 
 

 

 

18 November 2008

Tiling in lounge.

When all the tiling is completed, the doors and windows can be measured and ordered.

 

 

 

 
 

 

 

18 November 2008

Lounge and kitchen. Kitchen tiles are black in colour. A breakfast bar will separate the kitchen.

 

 

 

 
 

 

 

18 November 2008

Start of the construction of the pool. All the fabrication panels have been delivered so the construction should not take too long.

 

 

 

 
 

 

 

21 November 2008

Swimming pool cast in concrete from a metal frame which gives the walls a very smooth finish.

 

 

 

 
 

 

 

21 November 2008

The steps are a nice shape but the pool looks deeper than it should be at the deep end. Maybe there is more infilling to do at the bottom.

 

 

 

 
 

 

 

21 November 2008

The stone has been delivered for the facing of the walls around the porch.

 

 

 

 
 

 

 

29 November 2008

Ground levelling at rear and compressed with crushed stone ready for shuttering and concrete.

 

 

 

 

 
 

 

 

29 November 2008

Small wall at one end of the covered veranda. Against the wall inside will be a barbecue with kitchen units either side.

 

 

 

 

 
 

 

 

29 November 2008

Start of stone facing around the porch.
The porch has also been tiled.

 

 

 

 

 
 

 

 

29 November 2008

The veranda outside the bedroom has been tiled.

 

 

 

 

 
 

 

 

29 November 2008

The main covered veranda has been tiled.

The concrete pillars at the end which will hold up the roof will be faced with stone.

 

 

 

 

 
 

 

 

29 November 2008

The steps down to the kitchen.

 

 

 

 

 