Custom Build Bungalow at Arodes

 

Click for Paphos, Cyprus Forecast

Click here for Jan 12 - to date    The Latest

Click here for Sep 11 - Dec 11    

Click here for Sep 10 - Aug 11  

Click here for Dec 09 - Jul 10

Click here for Aug - Nov 09

Click here for May - Jul 09

This page = Feb - Apr 09   

Click here for Dec - Jan 09

Click here for Oct - Nov 08

Click here for Jul - Sep 08

Click here for May - Jun 08

Click here for Mar - Apr 08

Click here for Jan - Feb 08

Click here for Nov - Dec 07

Click Here for Sep - Oct 07 

Click here for Oct 06 - Aug 07   The Start

Click here for Plan View

 

 

 

 

 

6 February 2009

Nearly finished at the rear..

 

 

 

 

 
 

 

 

6 February 2009

Fireplace finished.

 

 

 

 

 

 
 

 

 

6 February 2009

Shower in ensuite wet room

 

 

 

 

 

 

 
 

 

 

6 February 2009

All doors and door handles now fitted. This is the second bedroom.

 

 

 

 
 

 

 

6 February 2009

Kitchen nearly complete.

 

 

 

 

 
 

 

 

6 February 2009

Doors along hallway.

The inside of the house is now about a week away from being finished.

Occupation now depends on the completion of the essential external jobs including:
Covered pergola over veranda
Barbeque & units on veranda
Water supply to property
Electrical supply to property
Driveways
Paths down sides
Sceptic tank and drainage

 

 

 

 
 

 

 

8 February 2009

Utility room finished apart from door handles. Space for large fridge and washing machine.

 

 

 

 

 
 

 

 

14 February 2009

Washbasin in en suite.

No progress over the last week apart from carpenter finishing off inside.

 

 

 
 

 

 

22 February 2009

Very little progress since 8th Feb. This is the barbecue being assembled.

 

 

 

 

 
 

 

 

22 February 2009

Nice large barbecue (good for parties)
and includes a sink.

 

 

 

 

 
 

 

 

22 February 2009

A 'plaque' inlaid into the wall in the porch.

 

 

 

 
 

 

 

22 February 2009

Some of the 'plaques' inlaid in to the wall of the lobby. They will all be painted over the same colour as the wall.

 

 

 

 

 
 

 

 

14 March 2009

Air conditioning units on external walls.

 

 

 

 

 
 

 

 

14 March 2009

Air conditioning unit in kitchen

 

 

 

 

 
 

 

 

14 March 2009

Barbecue unit fitted on veranda.

No real progress since 8th February. Very disappointing. This project is now 12 months late. I'm glad we have penalty clauses in the contract.

 

 

 

 

 
 

 

 

29 March 2009

Hot and cold water tanks plus solar panel on flat roof. The hot water is heated by the solar panel whenever the sun is shining. It can also be heated by the central heating and by immersion heater.

The stonework has been pointed.

 

 

 
 

 

 

29 March 2009

The cover for the veranda under construction.

 

 

 

 

 
 

 

 

29 March 2009

Another picture of the covered veranda. The roof will be tiled and railings provided along the front.

Some good news - after the torrential rain this last week, the basement remained dry.

 

 

 
 

 

 

5 April 2009

Drives compacted with hardcore and shuttering along sides. Steel reinforcing will be placed on drive before concrete poured.

 

 

 

 
 

 

 

5 April 2009

Drive taken from the other entrance.
A lot of landscaping to be done after we move in, now who can I call on to help?

 

 

 

 
 

 

 

5 April 2009

Roof finished on covered veranda.

 

 

 

 

 
 

 

 

6 April 2009

The drives being concreted. An important milestone which allows the last set of jobs to be finished.

 

 

 

 

 
 

 

 

6 April 2009

The pad on the left is for the electric meter enclosure.

 

 

 

 

 
 

 

 

6 April 2009

Man-handling the concrete pump.

 

 

 

 

 
 

 

 

6 April 2009

The manhole is for the water supply.

 

 

 

 

 
 

 

 

6 April 2009

Another view. The drive will be finished today and walkable tomorrow.

 

 

 

 

 

 
 

 

 

9 April 2009

Driveway useable, central heating units being delivered.

 

 

 

 

 
 

 

 

16 April 2009

More concrete arriving, this time for the path around sides of house and the base for the gas tank and satellite dish.

 

 

 

 
 

 

 

16 April 2009

Concrete around the front and left side.

 

 

 

 

 
 

 

 

16 April 2009

Concrete slab for gas tank and dish.

 

 

 

 

 
 

 

 

16 April 2009

Kitchen appliances installed.
Oven and microwave and dishwasher to the left.

 

 

 

 
 

 

 

16 April 2009

Hob and sink.

 

 

 

 

 
 

 

 

16 April 2009

Radiators installed.

We have decided to move in on 28th April whether or not the house is ready.

At the time of writing there is no electric and no sceptic tank for waste as well as many other jobs not yet completed.
Watch this space for World War 3.

 

 
 

 

 

17 May 2009

We moved in as planned on 28th April and are now finally getting a bit straight.

No world war, and generator and services were done in the nick of time.

 

 

 

 

 

 
 

 

 

17 May 2009

Covered Veranda.

 

 

 

 

 
 

 

 

17 May 2009

Lower veranda

 

 

 

 

 
 

 

 

3 May 2009

Barbecue on my birthday.
I feel a lot older than 34!

 

 

 

 

 
 

 

 

3 May 2009

It was a cold day.

 

 

 

 

 
 

 

 

17 May 2009

Sorting the office.

 

 

 

 

 
 

 

 

17 May 2009

The diesel generator which is supplying electricity, and a 1000 Litre diesel oil tank.

 

 

 

 

 
 

 

 

17 May 2009

The pool pump and filter. The room is not completed..

 

 

 

 

 
 

 

 

17 May 2009

Satellite dish and 1000 lt propane gas tank.

 

 

 

 

 
 

 

 

17 May 2009

The boiler room (central heating) which will also hold garden tools etc.

 

 

 

 

 

 
 

 

 

17 May 2009

Boiler room has been built filling a corner. Door still to be fitted.

 

 

 

 
 

 

 

17 May 2009

A lot of the rubbish has been cleared away.

 

 

 

 
         
         
         
     