7 July 2008
Bricks delivered.
Bricking starts 8 July together with roof waterproofing and tiling.
|
|
|

|
|
8 July 2008
Brickwork started.
|
|
|

|
|
15 July 2008
Brickwork nearly finished.
|
|
|

|
|
15 July 2008
|
|
|

|
|
15 July 2008
From the rear.
All the openings at the rear are
patio sliding doors
|
|
|

|
|
15 July 2008
Kitchen
|
|
|

|
|
15 July 2008
Lounge / dining room
|
|
|

|
|
15 July 2008
|
|
|

|
|
15 July 2008
|
|
|

|
|
22 July 2008
Brickwork almost complete.
Roof waterproofed and tiles delivered.
The white area in the porch is polystyrene acting as a former until brickwork
dries.
|
|
|

|
|
22 July 2008
Internal walls rendered ready for services (electric, water, heating
etc) then plaster.
|
|
|
|
|
27 July 2008
Almost all internal brickwork complete and rendered ready for provision
of services. Services are fed in pipes up walls (larger pipes cut in)
and along floors. Wall plaster and floor screed then covers these.
|
|
|

|
|
31 July 2008
Tiling & brickwork finished. No more work now until September. The
Cyprus building industry traditionally does not work during August because
of the excessive temperatures.
|
|
|

|
|
31 July 2008
Next job is to mark the positions of all the electrical points, lights
and switches and also the central heating radiators.
Pipes and conduits for these are then laid before plastering and floor
screed. External rendering will also be completed next.
|
|
|

|
|
28 August 2008
Man with clipboard, discussing the electrical services.
|
|
|

|
|
5 September 2008
Making good progress with external and internal plastering.
|
|
|

|
|
5 September 2008
Position of electrical services chased in walls. This is for switches
and lights above bed plus power points below.
|
|
|

|
|
11 September 2008
Central heating pipes to be terminated on manifolds on the wall. The
manifolds will then be connected to the boiler in the external boiler
room.
|
|
|

|
|
11 September 2008
Hot, cold and drinking water supplies for the kitchen. The white pipes
are for air conditioning compressors mounted externally.
|
|
|
|
|
16 September 2008
Central heating and water pipes distribution.
|
|
|

|
|
20 September 2008
Shuttering for extension of retaining wall to enable back filling for
veranda base slab.
|
|
|

|
|
20 September 2008
Electrical conduits in place.
|
|
|

|
|
20 September 2008
Left hand side of house showing water manifolds below bedroom windows.
|
|
|

|
|
20 September 2008
Hot and cold water manifolds for central heating and water supplies.
|
|
|

|
|
28 September 2008
Right hand side of house, retaining walls extended to allow ground level
to be raised at the back of the lounge for the veranda.
|
|
|

|
|
28 September 2008
Floor levels completed and last walls built in the lounge / hallway /
office.
|
|
|
|
|
28 September 2008
Electrical consumer unit in the basement. A similar unit is also fitted
in the ground floor lobby.
|
|
|
|
|
Next Page Oct - Nov 08 |
|
|
|
|
|
|
|
|
|
|
|
 |
 |
 |
 |
 |