10 December 2008
Stonework around the porch.
|
|
|

|
|
10 December 2008
Close up of stonework. We are very pleased with the design with each
piece of stone cut to shape by hand.
|
|
|

|
|
10 December 2008
Concrete base laid around the pool and down to the basement ready for
tiles.
|
|
|

|
|
10 December 2008
Another view of the slope down to the Gum Tree Guest Suite on the lower
floor.
|
|
|

|
|
13 December 2008
Stonework round porch completed and stone capping on retaining wall.
|
|
|

|
|
13 December 2008
Stone edging round both tiled verandas.
|
|
|

|
|
13 December 2008
Pool and surround which will be tiled, picture taken from the covered
veranda.
|
|
|

|
|
13 December 2008
Marble steps down to the basement studio.
|
|
|

|
|
13 December 2008
Basement veranda - walls rendered and capped with stone.
|
|
|

|
|
13 December 2008
Nice space at one end of pool. This area is now ready for tiling.
|
|
|

|
|
13 December 2008
Stone steps between verandas.
|
|
|

|
|
25 December 2008
No progress at all since 13th Dec. Still waiting for doors and windows
and in the last few days we have had storms and torrential rain which
has flooded most floors. Not our best Christmas !!
|
|
|

|
|
31 December 2008
Most doors and windows fitted.
Now the inside is secure and weatherproof, we hope to see rapid progress
by the carpenter, plumber and electrician.
|
|
|

|
|
31 December 2008
We asked for window sills to be exposed on the inside, which is not normal
practice in Cyprus.
|
|
|

|
|
31 December 2008
Left hand side.
|
|
|

|
|
31 December 2008
Part of the lounge
|
|
|

|
|
31 December 2008
The Gum Tree Visitors suite in the
basement.
|
|
|

|
|
31 December 2008
A blonde prowler caught on camera
at the rear
|
|
|

|
|
6 January 2009
Stone work finished and most windows and doors fitted
|
|
|

|
|
6 January 2009
Kitchen unit carcass's made off site and delivered.
|
|
|
|
|
6 January 2009
Door frames in position
|
|
|
|
|
6 January 2009
Built in cupboards in the office.
|
|
|
|
|
6 January 2009
Built in wardrobe in second bedroom.
Design is white oak.
|
|
|

|
|
11 January 2009
Kitchen units being built. Design is white doors, black worktop.
Appliances include - oven, microwave, built in fridge, dish washer, hob,
sink.
|
|
|

|
|
11 January 2009
Units being built in Utility room. Appliances include a full size fridge,
washing machine and sink.
|
|
|

|
|
11 January 2009
Basement veranda and walkway ready for tiling.
|
|
|

|
|
11 January 2009
Coping stones fitted to pool. The pool area is now ready for tiling.
|
|
|

|
|
14 January 2009
Basement patio tiled
|
|
|

|
|
14 January 2009
We have a front door. The house is now secure.
|
|
|

|
|
14 January 2009
Stone around the pillars that will support the roof of the covered veranda.
|
|
|
|
|
16 January 2009
Tiling in main bathroom.
|
|
|
|
|
16 January 2009
Tiling in en-suite bathroom.
|
|
|

|
|
16 January 2009
Start of tiling round the pool.
|
|
|

|
|
21 January 2009
Start of build of fireplace. It will be faced in stone.
|
|
|

|
|
21 January 2009
Built in wardrobe in the basement studio.
Man in doorway is painting in the store room.
|
|
|

|
|
21 January 2009
Colour swatches on the wall, more decisions, don't like any of these!!
|
|
|
|
|
23 January 2009
Progress on the fireplace and the
chimney is built external.
|
|
|

|
|
23 January 2009
Tiling finished in the bathrooms.
|
|
|

|
|
23 January 2009
Tiling up the ramp.
|
|
|

|
|
28 January 2009
Second coats of paint on outside.
|
|
|
|
|
28 January 2009
Fitted wardrobes in second bedroom.
|
|
|

|
|
28 January 2009
Fitted wardrobes in master bedroom.
|
|
|

|
|
28 January 2009
Fitted wardrobes in basement studio.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Next Page |
|
 |
 |
 |
 |
 |